- Completed excavation of new drainage lines adjacent to Passarelle redesign section
- Installed new 10” drainage pipe and connection to the storm drain system on First Street
- Began stone tile installation on the fountain
- Completed installing, grading and compaction the final base layers for the new First Street asphalt street
- Completed the curb & gutter concrete on the east side of First Street to Passarelle redesign section
- Constructed a barrier swale for the asphalt adjacent to the Passerelle redesign section
- Continued excavation for new foundations , irrigation and electrical conduit on State Street
- Completed grading and compaction of north side of Main Street sidewalk adjacent to Foothill
- Installed new rain and erosion barriers on project perimeters
- Completed re-engineering work for sidewalk transition and ground elevations on State Street at First Street
Downtown Traffic Updates
- First Street paving was delayed on Friday, November 4 due to rain.
- The first layer (lift) of asphalt is in progress today, Monday, November 7. The second lift date will be determined this week.
Other Downtown News
- The Downtown Holiday Stroll is this Friday, November 11 from 5-9pm: Shops open! Music, food and entertainment; for more details, click here!
- Install tile for new fountain
- Demolish the State St curb & gutter adjacent to the project
- Install final layers of aggregate and soil for the new First Street roadbed
- Pave the first layer (lift) of asphalt on First Street
- Complete the stone tile installation on First Street Fountain
- Continue work on new traffic signal control box
- Continue landscaping area preparation
- Continue gas line connection work
- Continue engineering design work on sidewalk transition and ground elevations on State Street at First Street
- Removal of the City’s Field Office (temporary trailer) in First Street parking lot
- Excavate and pour concrete for First Street planter wall near State Street
- Re-grade and compact Central Plaza sidewalk
- Set and pour concrete bands adjacent to Central parking plaza
- Remove temporary sidewalk at Main Street