Completed October 31-November 4
  • Completed excavation of new drainage lines adjacent to Passarelle redesign section
  • Installed new 10” drainage pipe and connection to the storm drain system on First Street
  • Began stone tile installation on the fountain
  • Completed installing, grading and compaction  the final base layers for the new First Street asphalt street
  • Completed the curb & gutter concrete on the east side of First Street to Passarelle redesign section
  • Constructed a barrier swale for the asphalt adjacent to the Passerelle redesign section
  • Continued  excavation for new foundations , irrigation and electrical conduit on State Street
  • Completed grading and compaction of north side of Main Street sidewalk adjacent to Foothill
  • Installed new rain and erosion barriers on project perimeters
  • Completed re-engineering work for sidewalk transition and ground elevations on State Street at First Street

Downtown Traffic Updates
  • First Street paving was delayed on Friday, November 4 due to rain.
  • The first layer (lift) of asphalt is in progress today, Monday, November 7. The second lift date will be determined this week.

Other Downtown News
  • The Downtown Holiday Stroll is  this Friday, November 11 from 5-9pm: Shops open! Music, food and entertainment; for more details, click here!
Scheduled for This Week
  • Install tile for new fountain
  • Demolish the State St curb & gutter adjacent to the project
  • Install final layers of aggregate and soil for the new First Street roadbed
  • Pave the first layer (lift) of asphalt on First Street
  • Complete the stone tile installation on First Street Fountain
  • Continue work on new traffic signal control box
  • Continue landscaping area preparation
  • Continue gas line connection work
  • Continue engineering design work on sidewalk transition and ground elevations on State Street at First Street
  • Removal of the City’s Field Office (temporary trailer) in First Street parking lot
  • Excavate and pour concrete for First Street planter wall near State Street
  • Re-grade and compact Central Plaza sidewalk
  • Set and pour concrete bands adjacent to Central parking plaza
  • Remove temporary sidewalk at Main Street
 