Completed October 24 - 28- Completed the curb and gutter along the west-side of First Street
- Installed the internal water lines and return basin on the First Street fountain
- Poured the cement for the fountain and prepped for the tile installation next week
- Completed grading and installing the first layer of base rock (aggregate) on First Street
- Completed the curb & gutter concrete on the west side of First Street
- Continued work on the gas line connection in the Central Plaza
- Completed demolition of asphalt, curb and gutter on State Street
- Began excavation for new foundations , irrigation and electrical conduit on State Street
- Completed excavation for planting wall “A” on First Street; then framed and poured concrete foundation for planting wall “A”
- Completed forms and finished pouring concrete for new mid-block crosswalk on First Street
- Capped new manhole on First Street near State Street
Downtown Traffic Updates- First Street paving has been scheduled: first asphalt layer (lift) will take place Friday. November 4 and the second layer (lift) Monday, November 7.
- First Street will re-open to one-way traffic (southbound direction) on Friday, November 11
Other Downtown NewsScheduled for New Week- Install tile for new fountain
- Demolish the State St curb & gutter adjacent to the project
- Install final layers of aggregate and soil for the new First Street roadbed
- Complete grading and compacting of new roadbed in preparation for paving
- Pave the first layer (lift) of asphalt on First Street
- Continue work on new traffic signal control box
- Continue landscaping area preparation
- Continue gas line connection work
- Continue engineering design work on sidewalk transition and ground elevations on State Street at First Street
|