- Continued laying storm drain pipe, working from State Street towards Parking Plaza North– 90% completed
- Continued excavation of dirt below street level in preparation for the new sub-base and asphalt top of the new streets—90% completed
- Complete trenching and laying of new electrical & irrigation lines on Main Street
- Poured fortified concrete cap for water lines on First and Main Streets– 90% complete
- Trenched for new streetlight electrical conduit on Main Street and began on First Street
- Continued building curb and gutter frames
- Compacted First & Main intersection soil in preparation for Geo-fabric and base rock
- Installed new storm drain manhole on First Street
- Backfilled and placed asphalt (paved) trench on First Street over new storm drain pipe
- Water company crew night work to place the water pipe below other utility lines on First Street and connect to the main water line on the Central Parking Plaza
- No work will take place on the job site over the Labor Day weekend
- Beginning Tuesday, September 6, crews will work 10-12 hour days and weekends
- The tentative opening date for the First & Main intersection has been revised to Monday, September 26. This will be the entire intersection all the way out to Foothill Expressway, instead of opening one segment at a time.
- A more detailed update on the opening phases will be distributed next week, mid-week.
Scheduled for September 6-10
- Begin working 10-12 hours daily, Monday through Sunday
- Remove the two sewer manholes in the First & Main intersection and replace with new lower covers and cones (carry over from last week)
- Continue installing Geo-fabric and base rock for the new road bed
- Finish excavation of below grade dirt for street sub-base along First Street near water pipe
- Complete final manhole of new storm drain on First Street and connect to the main system
- Begin saw cutting First Street sidewalk from State Street to the North Plaza for irrigation & electrical lines (carry over from last week)
Traffic Update
- Temporary lane closure on First Street between State and Parking Plaza North will continue with flaggers during work hours until manhole complete
- Installed new traffic loops (sensors) at the Edith Avenue and First Street intersection this week to correct the commute backup on Foothill & Edith Ave
- Began distributing Annie’s Downtown contact cards to businesses.
- Diagram of phased road openings will be distributed next week, mid-week.
RSS Feed