Completed this week:
• 90% of the curbs & gutters within the project area have been removed
• 100% of the old electrical conduit along First Street has been removed
• Installed temporary street lights along First Street and the start of State Street (these will be removed when the new street lights are installed)
• The City Council approved a design change that saves two mature London Plane trees  in front of Skip’s Pizza on First Street
• City Council also approved design changes to the sidewalk paving and a new benchwall along First Street near State Street
• Installed new gas line along First Street using new earthquake-safe flexible gas piping
• Removed the unexpected concrete slap in the center of the First & Main intersection
• Installed fabric blocks on top of all storm drain catch-basins to prevent any construction debris getting into the drain and ultimately the creek
• Hauled 100% of all concrete & asphalt debris demolished away for recycling
• Prepared the curb & gutter areas for placing the concrete molds next week

Scheduled for the week of August 8-12
• Create concrete molds (formwork) for new curb and gutter installation
• Pour new concrete for curbs & gutters adjacent to First & Main intersection area
• Fill-in & compact all gas trenches (backfill)
• Dig new sewer trench
• Remove trees as determined by revised plan
• Install straw waddles and fencing around remaining trees to protect them during construction
• Contractor will begin working on Saturdays for the next few weeks

Traffic Update
• One way traffic on First Street between State & Plaza North 7:00 am to 5:00 pm while trenching.

Unexpected Finds - Surprises
• The concrete cap on top of the new water line may need to be moved deeper underground to prevent interfering with the new road bed. The City Engineer will meet with Cal Water engineers to determine next step

Outreach Updates
• New Apricot Annie parking signs were installed to highlight free parking areas
• Two new signs highlighting access to the Chevron gas station installed
• Revised directional signs for drivers were installed on San Antonio Rd, El Monte Ave, Foothill Expressway
• More permanent Downtown directional signs installed
• Sidewalk A-frames directing walkers to businesses along First Street installed
• Apricot Annie continued meeting with community groups to ask for input and provide updates. If your group is interested in a visit from Annie, please email Beverly at btucker@losaltosca.gov
 
 
  1. Yesterday (7.18.11), sidewalk cuts were to assist in removing the concrete later. 

  2. Today (7.19.11), a large machine called a cold planer removed the paving asphalt along First Street from the intersection from Main St to the intersection of State. The State Street intersection will remain intact until work begins on that intersection.

  3. This morning, additional road closure and directional signs were added on Foothill Expressway at Main Street and on First Street to let driver's know that the Chevron station is open for business but the street is closed to through traffic.

  4. The first of the Apricot Annie signs were installed Sunday, July 17. More will be installed over the next two weeks. The signs are currently on temporary holdings and will be put up on permanent posts in the next week.

 
 
Picture
  1. Meet Apricot Annie! Annie will be featured on the many signs letting people know businesses are open and showing people where to park. These signs will be rolled out over the next week with the first round going up Sunday evening.

  2. Traffic detour signs required by the State of California are in place and ready to be unwrapped Monday morning. Some of these signs are on permanent posts and some are on temporary sawhorses. These signs are reflective orange and black to meet the State code.

  3. Annie's "Get-Around-Guide" with the best routes for visiting downtown is in the works and will be posted online at the end of next week.

 
 
1.       Underground utilities are currently being marked on the pavement/sidewalks. These are needed so gas and electricity
          are not turned off while cuts are made in the concrete or pavement is removed.

2.       The first of the basic traffic construction signs required by Caltrans will begin being installed in the next few days.

3.       Signs promoting businesses are open and free parking are being prepared now for installation next week.

4.       This Friday, the first saw-cuts into sidewalks will be made in areas that won’t disrupt car or foot traffic. Most of the heavy
           demolition work will begin Monday, July 18