Completed October 31-November 4
  • Completed excavation of new drainage lines adjacent to Passarelle redesign section
  • Installed new 10” drainage pipe and connection to the storm drain system on First Street
  • Began stone tile installation on the fountain
  • Completed installing, grading and compaction  the final base layers for the new First Street asphalt street
  • Completed the curb & gutter concrete on the east side of First Street to Passarelle redesign section
  • Constructed a barrier swale for the asphalt adjacent to the Passerelle redesign section
  • Continued  excavation for new foundations , irrigation and electrical conduit on State Street
  • Completed grading and compaction of north side of Main Street sidewalk adjacent to Foothill
  • Installed new rain and erosion barriers on project perimeters
  • Completed re-engineering work for sidewalk transition and ground elevations on State Street at First Street

Downtown Traffic Updates
  • First Street paving was delayed on Friday, November 4 due to rain.
  • The first layer (lift) of asphalt is in progress today, Monday, November 7. The second lift date will be determined this week.

Other Downtown News
  • The Downtown Holiday Stroll is  this Friday, November 11 from 5-9pm: Shops open! Music, food and entertainment; for more details, click here!
Scheduled for This Week
  • Install tile for new fountain
  • Demolish the State St curb & gutter adjacent to the project
  • Install final layers of aggregate and soil for the new First Street roadbed
  • Pave the first layer (lift) of asphalt on First Street
  • Complete the stone tile installation on First Street Fountain
  • Continue work on new traffic signal control box
  • Continue landscaping area preparation
  • Continue gas line connection work
  • Continue engineering design work on sidewalk transition and ground elevations on State Street at First Street
  • Removal of the City’s Field Office (temporary trailer) in First Street parking lot
  • Excavate and pour concrete for First Street planter wall near State Street
  • Re-grade and compact Central Plaza sidewalk
  • Set and pour concrete bands adjacent to Central parking plaza
  • Remove temporary sidewalk at Main Street
 
 
Work was suspended several days this week due to rain
  • Finished preparing potential run-off areas for rain– covering exposed soil slopes with tarps, installing straw wattles along potential run off areas and covering storm drains with permeable cloth to keep debris out of the drains 
  • Continued work on new traffic controller next to Foothill Expressway                                                                                                                       
  • Completed temporary asphalt walkways through the landscaping areas adjacent to the First & Main intersection
  • Completed metal rebar for the first stone monument foundation
  • Completed excavation for the fountain foundation on First Street
Traffic Update
  • October 8 & 9- Micro sealing on San Antonio Road between Foothill Expressway and Pine Lane will be completed. One lane in each direction will remain open during the sealing. Some intersections will have detours marked by signs
Safety Training
  • All contractor crew members attended remedial safety training on utility markings and excavation protocols following last week’s gas line break
Scheduled for October 3-
  • Continue pouring concrete for new curbs along First Street
  • Continue grading on First Street roadbed
  • Continue work on new traffic signal control box
  • Begin construction of new 6” lateral sanitary sewer line on First Street (near State St)
  • Continue work on signal lights and signal controller box
  • Continue excavation for new irrigation lines