Completed November 14-18- Completed 100% of concrete curbs and gutters for entire project
- Completed spreading aggregate and soil for new First Street roadbed
- Completed final grading and compacting of new roadbed
- Removed transition asphalt in State St & First St intersection
- Completed second layer (lift) of asphalt for First Street
- Installed temporary street markings for cars on First Street
- Set form and poured new concrete for Central Plaza parking plaza
- Installed final disabled accessible (ADA) sidewalk ramp in project area
- Completed installing stone face on fountain and new planter
- Began installation of fountain pump
- Completed trenching for new electrical and irrigation lines on State Street
- Connected (tied) electrical conduit in Central Plaza
- Poured the cement footings for the new First Street trellis bases
- Constructed form for long planter wall on First Street
- Begin pouring cement for long planter wall
Other Downtown News- The annual Festival of Lights Parade is Sunday, November 27 at 6:00 pm. Don’t miss this wonderful event! For more information, visit www.losaltosparade.com
- The City’s Field Office trailer has been removed from the all day parking lot on First Street, freeing up parking stalls!
- Traffic Updates
- There was confusion over the traffic lanes on First Street this week. Annie’s Phased Opening Map has been revised for clarity. See the new map here: www.firststreetlosaltos.org/phased-opening-map.html
- First Street is now open to cars during non-construction hours in the southbound direction! The northbound direction will be used temporarily for pedestrians while the sidewalks are completed. It will re-open to cars as soon as they are complete
- The traditional no parking areas for the Festival of Lights parade will be closed on Sunday, November 27. For details on the parade route, visit www.losaltosparade.com
Scheduled for November 21-December 2- Install temporary pedestrian access for Skip’s Pizza and along First Street
- Remove old sidewalk on First Street between Main St and Central Plaza
- Grade new sidewalk section and place base rock
- Remove forms on long planter wall
- Set forms and install rebar for new sidewalk
- Continue irrigation line installation and wiringon First Street
- Install new traffic bollard on the north-east corner of First and Main
- Pour walkway cement on First Street
- Continue electrical work on new traffic signal box
PLEASE NOTE: Construction work will not take place on November 24 & 25. The weekly construction meeting will not be held on November 24. Apricot Annie will be out of the office November 21-27. City offices will be closed November 24 & 25.
Completed October 31-November 4 - Completed excavation of new drainage lines adjacent to Passarelle redesign section
- Installed new 10” drainage pipe and connection to the storm drain system on First Street
- Began stone tile installation on the fountain
- Completed installing, grading and compaction the final base layers for the new First Street asphalt street
- Completed the curb & gutter concrete on the east side of First Street to Passarelle redesign section
- Constructed a barrier swale for the asphalt adjacent to the Passerelle redesign section
- Continued excavation for new foundations , irrigation and electrical conduit on State Street
- Completed grading and compaction of north side of Main Street sidewalk adjacent to Foothill
- Installed new rain and erosion barriers on project perimeters
- Completed re-engineering work for sidewalk transition and ground elevations on State Street at First Street
Downtown Traffic Updates - First Street paving was delayed on Friday, November 4 due to rain.
- The first layer (lift) of asphalt is in progress today, Monday, November 7. The second lift date will be determined this week.
Other Downtown News- The Downtown Holiday Stroll is this Friday, November 11 from 5-9pm: Shops open! Music, food and entertainment; for more details, click here!
Scheduled for This Week - Install tile for new fountain
- Demolish the State St curb & gutter adjacent to the project
- Install final layers of aggregate and soil for the new First Street roadbed
- Pave the first layer (lift) of asphalt on First Street
- Complete the stone tile installation on First Street Fountain
- Continue work on new traffic signal control box
- Continue landscaping area preparation
- Continue gas line connection work
- Continue engineering design work on sidewalk transition and ground elevations on State Street at First Street
- Removal of the City’s Field Office (temporary trailer) in First Street parking lot
- Excavate and pour concrete for First Street planter wall near State Street
- Re-grade and compact Central Plaza sidewalk
- Set and pour concrete bands adjacent to Central parking plaza
- Remove temporary sidewalk at Main Street
Completed October 24 - 28- Completed the curb and gutter along the west-side of First Street
- Installed the internal water lines and return basin on the First Street fountain
- Poured the cement for the fountain and prepped for the tile installation next week
- Completed grading and installing the first layer of base rock (aggregate) on First Street
- Completed the curb & gutter concrete on the west side of First Street
- Continued work on the gas line connection in the Central Plaza
- Completed demolition of asphalt, curb and gutter on State Street
- Began excavation for new foundations , irrigation and electrical conduit on State Street
- Completed excavation for planting wall “A” on First Street; then framed and poured concrete foundation for planting wall “A”
- Completed forms and finished pouring concrete for new mid-block crosswalk on First Street
- Capped new manhole on First Street near State Street
Downtown Traffic Updates- First Street paving has been scheduled: first asphalt layer (lift) will take place Friday. November 4 and the second layer (lift) Monday, November 7.
- First Street will re-open to one-way traffic (southbound direction) on Friday, November 11
Other Downtown NewsScheduled for New Week- Install tile for new fountain
- Demolish the State St curb & gutter adjacent to the project
- Install final layers of aggregate and soil for the new First Street roadbed
- Complete grading and compacting of new roadbed in preparation for paving
- Pave the first layer (lift) of asphalt on First Street
- Continue work on new traffic signal control box
- Continue landscaping area preparation
- Continue gas line connection work
- Continue engineering design work on sidewalk transition and ground elevations on State Street at First Street
Completed September 23-30 - Installed top layer “2.5 inch lift” of asphalt for First & Main intersection and first 60’ of First Street
- Continued backfill over new base rock and compacting new soil on First Street
- Finished all demolition on Main St adjacent to Foothill Expressway
- Continued work on new traffic controller next to Foothill Expressway
- Installed the traffic loops (sensors) for the intersection signal lights
- Paved temporary sidewalk on west side of First Street and north side of Main Street adjacent to Foothill Expressway
- Installed ADA ramps to intersection crosswalks
- Installed straw wattles and erosion control fabric along 400 Main property.
- Dug footing and installed rebar for the first stone monument foundation
- Installed first irrigation lines for new landscape areas
- Installed temporary asphalt sidewalk sections through construction zones
- Installed temporary stop signs/road decals for intersection
- Striped street lanes & install reflective tabs
Traffic Update- First & Main intersection through to Foothill Expressway OPENED on Sunday, September 25!
Gas Line Incident September 29 - On Thursday, September 29, a gas line was ruptured during excavation on First Street. 911 as called at 10:38 am. Police arrived on the scene at 10:40 and Fire at 10:43. Evacuations of the block began at 10:41. PG&E arrived at 11:03 and the ruptured pipe was sealed at 11:11 am.
- There were no injuries, no explosion, no fire and no property damage as a result of the accident.
- Several businesses and restaurants were impacted for an hour by the evacuations and disruptions in gas service.
Downtown Traffic Events- Saturday & Sunday, October 1 & 2 FALL FESTIVAL in Parking Plaza North (parking plaza closed to cars beginning Friday evening, Sept 30)
Scheduled for October 3-7- Continue pouring concrete for new curbs along First Street
- Continue grading on First Street roadbed
- Continue work on new traffic signal control box
- Begin construction of new 6” lateral sanitary sewer line on First Street (near State St)
- Continue work on signal lights
- Continue excavation for new irrigation lines and fountain area
|