Completed September 10-16
  • Installed Geo-fabric and base rock along First Street
  • Completed 80% of backfill over new base rock and compacted new soil on First Street
  • Continued building curb and gutter frames
  • Poured concrete for the new curbs in the First & Main intersection
  • Poured the three concrete colors for the First & Main crosswalks
  • Completed the first new driveway for the Chevron station
  • Began demolition of the asphalt between First Street & Foothill Expressway
  • Completed removal of sidewalks leading to Foothill Expressway
  • Created concrete forms for new signal light bases
Schedule Update
  • Crews will continue to work 10-12 hour days during the week and will continue to work Saturdays and Sundays
Scheduled September 17-23
  • Continue setting curb and gutter forms along First Street
  • Continue pouring concrete for new curbs along First Street
  • Complete final grading of the First & Main intersection in preparation for new asphalt
  • Remove manholes from roadway adjacent to Foothill Expressway
  • Install new manholes adjacent to Foothill Expressway
  • First new asphalt layer will be paved in the First & Main intersection and 60 feet up First Street
  • New traffic signal loops will be installed for the First & Main intersection signal lights
Downtown Traffic Events
  • Friday, September 23– Los Altos High School Homecoming Parade!
  • Saturday, September 24– the 64th Annual Los Altos Kiwanis Pet Parade!
If you’d like the contact cards or phased  opening diagrams at your business, please call or email Beverly tel: 650-947-2889 btucker@losaltosca.gov