- Completed 100% of concrete curbs and gutters for entire project
- Completed spreading aggregate and soil for new First Street roadbed
- Completed final grading and compacting of new roadbed
- Removed transition asphalt in State St & First St intersection
- Completed second layer (lift) of asphalt for First Street
- Installed temporary street markings for cars on First Street
- Set form and poured new concrete for Central Plaza parking plaza
- Installed final disabled accessible (ADA) sidewalk ramp in project area
- Completed installing stone face on fountain and new planter
- Began installation of fountain pump
- Completed trenching for new electrical and irrigation lines on State Street
- Connected (tied) electrical conduit in Central Plaza
- Poured the cement footings for the new First Street trellis bases
- Constructed form for long planter wall on First Street
- Begin pouring cement for long planter wall
- The annual Festival of Lights Parade is Sunday, November 27 at 6:00 pm. Don’t miss this wonderful event! For more information, visit www.losaltosparade.com
- The City’s Field Office trailer has been removed from the all day parking lot on First Street, freeing up parking stalls!
- Traffic Updates
- There was confusion over the traffic lanes on First Street this week. Annie’s Phased Opening Map has been revised for clarity. See the new map here: www.firststreetlosaltos.org/phased-opening-map.html
- First Street is now open to cars during non-construction hours in the southbound direction! The northbound direction will be used temporarily for pedestrians while the sidewalks are completed. It will re-open to cars as soon as they are complete
- The traditional no parking areas for the Festival of Lights parade will be closed on Sunday, November 27. For details on the parade route, visit www.losaltosparade.com
- Install temporary pedestrian access for Skip’s Pizza and along First Street
- Remove old sidewalk on First Street between Main St and Central Plaza
- Grade new sidewalk section and place base rock
- Remove forms on long planter wall
- Set forms and install rebar for new sidewalk
- Continue irrigation line installation and wiringon First Street
- Install new traffic bollard on the north-east corner of First and Main
- Pour walkway cement on First Street
- Continue electrical work on new traffic signal box
Construction work will not take place on November 24 & 25. The weekly construction meeting will not be held on November 24. Apricot Annie will be out of the office November 21-27. City offices will be closed November 24 & 25.