- 50% of the sidewalks & gutters in the project area have been removed
- The surveying for the curbs & gutters has been completed. (more surveying will be done in each phase)
- Removed 90% of the old electrical conduit along First Street
- Turned off the traffic signal at First & Main with PG&E disconnecting all power to the traffic poles. This will be a significant power & cost savings.
- Installed “snow fencing” style barrier around work site as a safety precaution for pedestrians.
- The contractor is keeping the sidewalks & streets swept in areas immediately adjacent to the project, as required by the City
- Due to public interest, the tree removal along First Street was postponed while an alternative plan to retain some trees is drafted
- Begin trenching for the new gas line and storm drain pipes
- Begin laying the new gas line pipes
- Remove the concrete slab that was discovered under the paving in the center of the First & Main intersection.
- Begin spreading the class two rock aggregate (crumbled bits of rock that serve as a strong sub-base for the new sidewalks & roads)
- One way traffic on First Street between State & Plaza North 7:00 am to 5:00 pm while trenching.
- After further digging, it was learned that the concrete slab found under the First & Main intersection measured 80 ft long by 40 ft wide by 6 in deep. It may be part of a much earlier road as it approached the railroad tracks and crossing
- The new water line installed last fall along First Street will require relocating the planned storm water catch basin. This will not cause a construction delay but will change the type of catch basin used
- An old concrete cap from a water line no longer in use was also found. It will be removed in the next couple of weeks
- All sidewalk concrete and street paving removed from the project area will be recycled. This entails crushing the concrete and asphalt at an off-site location and then selling it to construction firms that may use it for new road construction
- Installation of Annie’s signs highlighting free parking areas began this week
- Approval to create two 20 minute parking stalls to help customers in the Central Parking Plaza were approved this week
- The City Council will consider design revisions regarding the First Street trees in the Streetscape Project on Wednesday, August 3 at 5:00 pm in the Council Chamber, One North San Antonio Road. Public is welcome!

RSS Feed